International School of Engineering Web Software development Development Decoded
Home Products Allmostapp Testimonials About Us
one pix   one pix   | |
Lessons  
Bookmark and Share
Add to Technorati Favorites

Lesson 4 - Level Resources

This entry is part 5 of 8 in the series Step-by-Step Project Planning with MS-Project

Previous Article in this Series
Lesson 3 - Allocate Resources and Set Timelines


After assigning resources to tasks and setting timelines, you must verify if one or more resources have been over-allocated in one or more tasks. In spite of your best planning efforts, this is quite likely to happen.

MS Project has an option to automatically level resources under the “Tools” menu. However, in order to be effective, this requires a lot more information to be input. Within the scope of this tutorial, we will only cover leveling resources manually.

  1. Select “Resource Usage” under the “View” menu to view the work allocated to each resource per day as shown in Figure 12. Check if any resource has been over-allocated. An over-allocated resource is shown in red. If any resource is over-allocated, check the days on which the resource is over-allocated using horizontal and vertical scrolls in the right pane of the screen. Rows highlighted in yellow in the right pane show the total time spent each day with effort spent on individual tasks in the rows with white background.
  2. Resource usage view

    Figure 12: Resource usage view
  3. On identifying a trouble-spot, go back to the “Gantt Chart” view using the “View” menu to fix it. You could:
    • fix the start and finish dates
    • modify predecessors
    • allocate the task to another resource who is available

    Go back and forth between these two views to identify and fix all over-allocation issues.

  4. celeroo-smiley Note: This must be done very systematically and urge to attempt quick fixes must be curbed. You must also note that fixing an over-allocation issue in one place can cause a new over-allocation issue in another place. However, a systematic approach will help you resolve these fairly quickly.
  5. At this point, you may want to assign cost for each resource. It is not compulsory to do this if you are not tracking the cost, but if you are, this will help you track how the project is faring in terms of the allocated budget. For doing this, highlight all tasks by clicking on the top-left cell as shown in Figure 13.
  6. Highlighting all cells of the project plan

    Figure 13: Highlighting all cells of the project plan
  7. Select “Assign Resources” under the “Tools” menu. In the “Assign Resources” window, double-click in the cost column against each resource to open another window to input “Resource Information”. In the “Costs” tab, enter the rates for the resource as shown in Figure 14.
  8. Setting the resource cost

    Figure 14: Setting the resource cost

Now each task has an associated cost. When you track the progress closely, you will know the health of the project both in terms of the schedule and the cost.

Next you must assign milestones, and finalize and create a baseline plan for tracking purposes.


Next Article in this Series
Lesson 5 - Assign Milestones and Finalize Plan



Discussion

Comments for “Lesson 4 - Level Resources”

 
OUR PRODUCTS
Celeroo Req 'n Spec
Smartest Way To Manage Requirements And Changes For Any Software Project   more
 
Free Trial Req 'n Spec
Celeroo Builder
Cheapest And Fastest Way To Build PHP Applications   more
 
Free Trial Builder
Celeroo Frame
Lean, Flexible And Transparent MVC PHP Framework       more
 
Download Frame

Subscribe to "Allmostapp: Empowering BAs to Build Apps from Ideas - Swiftly"

We will NOT share your info with any third party. PERIOD.
 
right-bg-img right-bg-img
  Who We Are | Contact Us  
  All Rights Reserved. Copyright © 2008 - 2017 International School of Engineering. Celeroo’s Blog and Training Center . Entries (RSS) Search Unleashed wordpress-email-newsletter-plugin-for-double-opt-in-subscription G Lock Powered by WordPress Theme by The Masterplan